71 PERMIT DECISION AND APPEAL PROCESSES
Administrative | Quasi-Judicial | Legislative | ||||
|---|---|---|---|---|---|---|
Process I | Process II | Process III | Process IV | Process V | Process VI | |
Preapplication Meeting | None | None | Optional | Recommended | Recommended | Recommended |
Notification Requirement | None | None | 500 feet | 500 feet | 500 feet | Citywide |
Neighborhood Meeting | None | None | Optional | Required | Required | Optional |
Written Report | None | Staff | Staff | Applicable Director | Applicable Director | Applicable Director |
Open Record Hearing | None | None | None | Hearing Examiner | Hearing Examiner | Planning Commission/ City Council |
Closed Record Hearing | None | None | None | None | City Council | None |
Decision-Maker | Applicable Director | Applicable Director/ Hearing Examiner1 | Applicable Director | Hearing Examiner | City Council | City Council |
Administrative Appeal | None | Hearing Examiner | Hearing Examiner | None | None | None |
Judicial Appeal | Superior Court | Superior Court | Superior Court | Superior Court | Superior Court | Growth Management Hearings Board or Superior Court |
Review Time Period | -- | 65 days | 100 days | 170 days | 170 days | -- |
Notes: |
|---|
1 Hearing examiner is decision-maker for Final Subdivision, Chapter 16.12 MMC. |
Process I | Process II | Process III3 | Process IV7 | Process V | Process VI |
|---|---|---|---|---|---|
Enforcement Action MMC Titles 5 – 18 | Code Interpretation MMC Titles 8 – 18 | Preliminary Short Plat Chapter 16.28 MMC | Preliminary Subdivision Chapter 16.12 MMC | Planned Development Master Plan Chapter 17.38 MMC4 | Code Amendment MMC Title 17 |
Engineering and Utilities MMC Titles 12, 13, 16 | Home Occupation Chapter 17.44 MMC | Modifications to Process IV | Binding Site Plan Chapter 16.30 MMC1 | Special Use Permit Chapter 17.42 MMC4 | Comprehensive Plan Amendment Chapter 17.67 MMC |
Clear and Grade Permit Chapter 13.26 MMC | Final Subdivision Chapter 16.12 MMC1, 2 | SEPA Threshold determination not otherwise combined Chapter 18.16 MMC | Macro Wireless Communication Facility Structures Chapter 17.58 MMC | Site-Specific Zoning Map Amendment5 | Citywide Zoning Map Amendment5 Chapter 17.68 MMC |
Storm Water Drainage Permit Chapter 13.26 MMC | Deviation from Standards | Shoreline Substantial Development Permit6 Chapter 18.12 MMC6 | Mobile Home Park Chapter 17.60 MMC1 | Shoreline Master Plan Amendment Chapter 18.12 MMC | |
Building Permit MMC Title 15 | Nonconforming Sign Chapter 17.50 MMC | Major Site Plan Approval Chapter 17.62 MMC | Conditional Use Permit Chapter 17.64 MMC | ||
Boundary Line Revision Chapter 16.29 MMC1 | Nonconforming Structures or Uses Chapter 17.52 MMC | Administrative Variance Chapter 17.65 MMC | Revocation of Decision All Processes | ||
Sign Permits Chapter 17.50 MMC | Critical Areas Decision (Map) Chapter 18.16 MMC1 | Variance Chapter 17.65 MMC3 | |||
Temporary Use Chapter 17.56 MMC | Design Review Chapter 17.43 MMC | Shoreline Permit Chapter 18.12 MMC | |||
Critical Areas or Exemption Chapter 18.16 MMC | Minor Site Plan Approval Chapter 17.62 MMC | Reasonable Use Exception | |||
Final Short Plat Chapter 16.28 MMC1 | |||||
Small Wireless Facilities and Macro Facilities on Existing Structures Chapter 17.58 MMC |
Notes: |
|---|
1 Required to be recorded. |
2 Before the hearing examiner, no administrative appeal. |
3 Neighborhood meeting optional. |
4 1,000- or 2,000-foot radius for notice. |
6 See Chapter 18.12 MMC for appeal procedures. |
7 1,000-foot radius for notice if project over 50,000 square feet or more than 50 units. |
Types I and II | 65 days |
Type III | 100 days |
Types IV and V | 170 days |
71 PERMIT DECISION AND APPEAL PROCESSES
Administrative | Quasi-Judicial | Legislative | ||||
|---|---|---|---|---|---|---|
Process I | Process II | Process III | Process IV | Process V | Process VI | |
Preapplication Meeting | None | None | Optional | Recommended | Recommended | Recommended |
Notification Requirement | None | None | 500 feet | 500 feet | 500 feet | Citywide |
Neighborhood Meeting | None | None | Optional | Required | Required | Optional |
Written Report | None | Staff | Staff | Applicable Director | Applicable Director | Applicable Director |
Open Record Hearing | None | None | None | Hearing Examiner | Hearing Examiner | Planning Commission/ City Council |
Closed Record Hearing | None | None | None | None | City Council | None |
Decision-Maker | Applicable Director | Applicable Director/ Hearing Examiner1 | Applicable Director | Hearing Examiner | City Council | City Council |
Administrative Appeal | None | Hearing Examiner | Hearing Examiner | None | None | None |
Judicial Appeal | Superior Court | Superior Court | Superior Court | Superior Court | Superior Court | Growth Management Hearings Board or Superior Court |
Review Time Period | -- | 65 days | 100 days | 170 days | 170 days | -- |
Notes: |
|---|
1 Hearing examiner is decision-maker for Final Subdivision, Chapter 16.12 MMC. |
Process I | Process II | Process III3 | Process IV7 | Process V | Process VI |
|---|---|---|---|---|---|
Enforcement Action MMC Titles 5 – 18 | Code Interpretation MMC Titles 8 – 18 | Preliminary Short Plat Chapter 16.28 MMC | Preliminary Subdivision Chapter 16.12 MMC | Planned Development Master Plan Chapter 17.38 MMC4 | Code Amendment MMC Title 17 |
Engineering and Utilities MMC Titles 12, 13, 16 | Home Occupation Chapter 17.44 MMC | Modifications to Process IV | Binding Site Plan Chapter 16.30 MMC1 | Special Use Permit Chapter 17.42 MMC4 | Comprehensive Plan Amendment Chapter 17.67 MMC |
Clear and Grade Permit Chapter 13.26 MMC | Final Subdivision Chapter 16.12 MMC1, 2 | SEPA Threshold determination not otherwise combined Chapter 18.16 MMC | Macro Wireless Communication Facility Structures Chapter 17.58 MMC | Site-Specific Zoning Map Amendment5 | Citywide Zoning Map Amendment5 Chapter 17.68 MMC |
Storm Water Drainage Permit Chapter 13.26 MMC | Deviation from Standards | Shoreline Substantial Development Permit6 Chapter 18.12 MMC6 | Mobile Home Park Chapter 17.60 MMC1 | Shoreline Master Plan Amendment Chapter 18.12 MMC | |
Building Permit MMC Title 15 | Nonconforming Sign Chapter 17.50 MMC | Major Site Plan Approval Chapter 17.62 MMC | Conditional Use Permit Chapter 17.64 MMC | ||
Boundary Line Revision Chapter 16.29 MMC1 | Nonconforming Structures or Uses Chapter 17.52 MMC | Administrative Variance Chapter 17.65 MMC | Revocation of Decision All Processes | ||
Sign Permits Chapter 17.50 MMC | Critical Areas Decision (Map) Chapter 18.16 MMC1 | Variance Chapter 17.65 MMC3 | |||
Temporary Use Chapter 17.56 MMC | Design Review Chapter 17.43 MMC | Shoreline Permit Chapter 18.12 MMC | |||
Critical Areas or Exemption Chapter 18.16 MMC | Minor Site Plan Approval Chapter 17.62 MMC | Reasonable Use Exception | |||
Final Short Plat Chapter 16.28 MMC1 | |||||
Small Wireless Facilities and Macro Facilities on Existing Structures Chapter 17.58 MMC |
Notes: |
|---|
1 Required to be recorded. |
2 Before the hearing examiner, no administrative appeal. |
3 Neighborhood meeting optional. |
4 1,000- or 2,000-foot radius for notice. |
6 See Chapter 18.12 MMC for appeal procedures. |
7 1,000-foot radius for notice if project over 50,000 square feet or more than 50 units. |
Types I and II | 65 days |
Type III | 100 days |
Types IV and V | 170 days |