§ 235-16.7

Temporary building permits; temporary certificates of occupancy.

A. 
A reasonable number of temporary construction trailers and offices for uses for which site plan approval has been granted may be allowed by the Building Inspector on a construction or development site by temporary certificate of occupancy until a permanent certificate of occupancy has been issued for the use for which site plan approval has been granted. The location of these facilities shall be approved by the Building Inspector. The applicant must provide the Building Inspector with all data reasonably necessary for him/her to issue such temporary permit(s), including an application and fee for such temporary permit(s). The temporary building permit(s) shall automatically expire and the trailers shall be removed prior to the issuance of the certificate of occupancy for the permanent building(s). The applicant must sign a written agreement of removal as a condition of receipt of the temporary certificate of occupancy.
B. 
Temporary residence certificates of occupancy for temporary living quarters, including mobile homes, may be issued by the Building Inspector to local residents for temporary emergency housing due to fire, natural disaster or other emergency or condition of extreme duress. Such temporary living quarters must otherwise meet all applicable setback requirements. Such certificates shall be valid, based upon a written agreement for removal, until a permanent certificate of occupancy is issued for the primary residence, but not for a period in excess of six months. The applicant must provide the Building Inspector with all data reasonably necessary for him/her to issue such temporary permit(s), including an application and fee for a temporary building permit.
C. 
Temporary permits for any temporary office of construction trailers for emergency use due to an unforeseen or catastrophic situation may be issued by the Building Inspector for the duration of the need but not more than six months, and removed based upon written agreement at such time that a new building permit or other certification of occupancy or use can be issued for that portion of the property for which the trailer or office was required. The applicant must provide the Building Inspector with all data reasonably necessary for him/her to issue such temporary permit(s), including an application and fee for a temporary building permit.