Sign Permit.
(a)
Purpose. The purpose of this section is to provide a procedure and requirement for obtaining a Sign Permit prior to the erection of certain signs as required by article G.
(b)
General Requirement. Unless specifically permitted by article G, no sign shall be erected, altered, or relocated after the effective date of this title until a Sign Permit has been secured from the Zoning Administrator.
(c)
Application Requirements. All applications for sign permits shall be made in writing on a form supplied by the City of Verona Zoning Administrator. Said application shall be submitted with all required information provided and shall conform to the rules and requirements adopted by the Zoning Administrator.
(d)
Procedure. The Zoning Administrator shall review the submitted application for compliance with the requirements of article G and subsection (c), above. Upon the receipt of a complete application, the Zoning Administrator shall issue an approved or denied Sign Permit based on the submitted application within five (5) working days of the acceptance of the complete application. The decision of the Zoning Administrator to deny a sign permit may be appealed to the Zoning Board of Appeals.
(e)
Termination of a Sign Permit. Any sign found not to be in compliance with the terms of this chapter shall be considered in violation of this chapter and shall be subject to all applicable procedures and penalties.
(f)
Fee. A fee is required for this procedure as set forth in the City Fee Schedule, as amended.
Sign Permit.
(a)
Purpose. The purpose of this section is to provide a procedure and requirement for obtaining a Sign Permit prior to the erection of certain signs as required by article G.
(b)
General Requirement. Unless specifically permitted by article G, no sign shall be erected, altered, or relocated after the effective date of this title until a Sign Permit has been secured from the Zoning Administrator.
(c)
Application Requirements. All applications for sign permits shall be made in writing on a form supplied by the City of Verona Zoning Administrator. Said application shall be submitted with all required information provided and shall conform to the rules and requirements adopted by the Zoning Administrator.
(d)
Procedure. The Zoning Administrator shall review the submitted application for compliance with the requirements of article G and subsection (c), above. Upon the receipt of a complete application, the Zoning Administrator shall issue an approved or denied Sign Permit based on the submitted application within five (5) working days of the acceptance of the complete application. The decision of the Zoning Administrator to deny a sign permit may be appealed to the Zoning Board of Appeals.
(e)
Termination of a Sign Permit. Any sign found not to be in compliance with the terms of this chapter shall be considered in violation of this chapter and shall be subject to all applicable procedures and penalties.
(f)
Fee. A fee is required for this procedure as set forth in the City Fee Schedule, as amended.