Sec 94.15.01 Purpose

The purpose of this Article is to establish requirements for nonconforming and substandard lots, nonconforming uses, nonconforming structures, and nonconforming sites created legally prior to March 18, 2015. Nonconforming signs are also addressed in Article 13.

Sec 94.15.02 Nonconforming And Substandard Lots

  1. No lot shall be created which does not meet the lot dimensional requirements of the associated zoning district.
  2. Legal nonconforming or substandard lots, as defined in Article 17, may be utilized as a building site for a permitted use (but not for a conditional use) in the associated zoning district, if all of the following apply:
    1. Such lot has never been developed with one or more of its structures placed partly on an adjacent lot or parcel.
    2. Such lot is developed to comply with this Chapter and other applicable chapters of the Weston Municipal Code.
  3. Conforming structures existing at the time of the adoption or amendment of this Chapter may be continued, although the lot does not conform to the newly adopted or amended requirements of this Chapter, as long as all uses on the lands containing the structure are legal conforming uses.
  4. Each aforementioned structure may be extended, enlarged, substituted, moved, remodeled, modified, added to, or rebuilt as long as any such change conforms to the established building setback lines along streets and the yard, height, and floor area ratio provisions of this Chapter.

[Amended via Ord. 15-009, 6/17/2015]

HISTORY
Amended by Ord. 19-001 on 1/23/2019

Sec 94.15.03 Nonconforming Uses

  1. Continuance of a Nonconforming Use. Any nonconforming use lawfully established prior to the date it became prohibited by this chapter may be continued without expansion and in a manner of operation existing upon such date, except as specified for nonconforming uses in this section.
  2. Modification of a Nonconforming Use. A nonconforming use shall not be expanded, enlarged, extended, or reconstructed unless the use qualifies under subsection (4).
  3. Discontinuance of a Nonconforming Use. When any nonconforming use of any structure or land is discontinued for a period of twelve consecutive months, or is changed into different use, any future use of said structure or land shall be in complete conformity with the provisions of this chapter.
  4. Maintenance and Repair of a Nonconforming Use. The ordinary maintenance and repair of a nonconforming use is permitted, including necessary repairs and incidental alterations that do not exacerbate the adverse impacts of the nonconforming use in relation to the intent and purpose of this chapter. Except as otherwise provided in this section, whenever a nonconforming use is damaged to the extent of more than 50 percent of the then-current equalized assessed value of the use and associated structure, such use shall not be restored except in conformity with the regulations of the district in which it is located. Notwithstanding the previous sentence, the structural repairs or alterations in a conforming structure containing a nonconforming use shall not during its lifetime exceed 50 percent of the equalized assessed value of said structure at the time of the first known structural repair or alteration, unless:
    1. The use within said structure is permanently changed to a conforming use, or
    2. The use is a nonconforming Single-Family Detached Residence and the total floor area of all additions permitted after September 1, 2025 does not exceed 25 percent of the residence’s floor area as of that date.


HISTORY
Amended by Ord. 25-011 on 8/18/2025

Sec 94.15.04 Nonconforming Structures

  1. Continuance of a Nonconforming Structure. Any structure lawfully established may be continued at the size and in a manner of operation existing upon such date, except as provided for nonconforming structures in this section.
  2. Expansion of a Nonconforming Structure. Any lawful nonconforming structure may be extended, enlarged, reconstructed, moved, or structurally altered, provided that said extension, enlargement, reconstruction, movement or alteration does not create any new violation of any setback or building requirements of the zoning district, nor increase the degree of the existing nonconformity except as:
    1. permitted under subsection (3),
    2. required by law or governmental order,
    3. required to comply with the provisions of this chapter, or
    4. in accordance with a variance granted by the Zoning Board of Appeals.
  3. Damaged or Destroyed Nonconforming Structure. A damaged or destroyed nonconforming structure may be restored to the size, location, and use that it had immediately before the damage or destruction occurred, without any limits on the costs of the repair, reconstruction, or improvement, if all of the following apply:
    1. The nonconforming structure was damaged or destroyed on or after March 2, 2006.
    2. The damage or destruction was caused by violent wind, vandalism, fire, flood, ice, snow, mold, or infestation.
  4. Unsafe Structures. Nothing in this Chapter shall preclude the Zoning Administrator from initiating remedial or enforcement actions when a lawful nonconforming structure is declared unsafe or presents a danger to the public health, safety, or welfare.
  5. Future Modification of a Nonconforming Structure. When any lawful nonconforming structure in any district is modified so as to be in conformance with the provisions of this Chapter, any future modification of said structure shall be in conformance with the provisions of this Chapter.
  6. Ordinary Maintenance of a Nonconforming Structure. Ordinary maintenance, repairs (including repairs reasonably necessary to prevent the deterioration of a structure), and remodeling of a nonconforming structure are permitted. Ordinary maintenance, repairs, and remodeling include internal and external painting, decorating, paneling, the addition of acoustical ceilings, the installation of heating, electricity, plumbing (including fixtures), insulation, and the replacement of doors, windows, and other non-structural components.
  7. Timing of Building Permit. Any structure for which a building permit has been lawfully granted prior to an amendment to this Chapter causing the structure or use to become nonconforming, may be completed in accordance with the approved plans, provided construction is started within 365 calendar days after issuance of the permit, and construction is completed within the term of the permit. If all such conditions are met, the construction or alteration within the scope of the permit shall not be deemed a change in the use or an expansion of the nonconformity for purposes of this section.

Sec 94.15.05 Nonconforming Sites

  1. Definition. A nonconforming site is one on which a principal use has been established prior to March 18, 2015 and on which one or more site development standards, such as minimum landscape surfaces, bufferyards, plantings, or minimum parking, have not been met or cannot be met owing to the configuration of the site or existing structures whether conforming or nonconforming.
  2. Blanket Variance. A blanket variance for the requirements of this Chapter is hereby granted to all development sites in their configuration existing or as finally approved as of March 18, 2015, except in the following circumstances:
    1. Where other Articles of this Chapter make a particular requirement applicable to existing development sites or components thereof.
    2. Where the predecessor zoning ordinance, or a Village zoning decision under that ordinance, required site improvements which have not been satisfactorily completed or maintained.
    3. Where a particular requirement of this Chapter reflects a condition or requirement of approval for the particular development site.
    4. Where the provisions of subsection (3) apply.
  3. Proposed Enlargements Require Compliance. After the March 18, 2015, additional site development that results in enlargement, expansion, or extension of uses or structures will not be allowed to occur without bringing the site into full compliance with all site development standards in this Chapter, or into compliance to the extent practical as provided in different sections of this Chapter, in accordance with the following:
    1. On lots where the site configuration and undeveloped area are sufficient to comply with nonconformities in site design, no enlargement, expansion, or extension of a use or structure shall be permitted if it makes compliance with site regulations of the Chapter impossible, even if said enlargement, expansion, or extension of the use or structure would otherwise be permissible.
    2. Enlargements, expansions, or extensions that would result in creation of one or more nonconformities, render a nonconforming site incapable of being brought into full or greater compliance with nonconforming site requirements, or increase the degree of existing nonconformities with the site development standards of this Chapter shall not be permitted, unless a variance is granted by the Zoning Board of Appeals under Section 94.16.11.
    3. On sites with adequate configuration and area to bring the site into full or greater compliance with the site design standards, in this Chapter said compliance shall be required at the time that site plan approval is necessary under Section 94.16.09. The degree to which each such site shall be made to comply with current site design standards shall be proportional to the degree of site improvement.
HISTORY
Amended by Ord. 23-016 on 10/20/2023