Administrative conditions of approval.
A.
A project which plats or subdivides land for sale and individual ownership shall properly record the plat with the Walla Walla County auditor prior to the issuance of any building permits or authorization to commence construction.
B.
A project proposing multiple land uses in a residentially zoned area shall complete construction of fifty percent of the residential part of the project prior to the issuance of building permits for any nonresidential constructions.
C.
Prior to the application for a building permit or other authorization to commence work, the project shall be accompanied by:
1.
Any bond required by the county guaranteeing completion of a specific defined portion of the project as authorized and approved, and/or a standard plat bond if subdivision and sale of lots is a part of the project;
2.
Deeds to any land or properties intended for public ownership and use in the completed project;
3.
A complete project site plan and construction plans and specifications for the initial buildings. (Ord. 269 (part), 2002; Ord. 329 §1(part), 2006)
Administrative conditions of approval.
A.
A project which plats or subdivides land for sale and individual ownership shall properly record the plat with the Walla Walla County auditor prior to the issuance of any building permits or authorization to commence construction.
B.
A project proposing multiple land uses in a residentially zoned area shall complete construction of fifty percent of the residential part of the project prior to the issuance of building permits for any nonresidential constructions.
C.
Prior to the application for a building permit or other authorization to commence work, the project shall be accompanied by:
1.
Any bond required by the county guaranteeing completion of a specific defined portion of the project as authorized and approved, and/or a standard plat bond if subdivision and sale of lots is a part of the project;
2.
Deeds to any land or properties intended for public ownership and use in the completed project;
3.
A complete project site plan and construction plans and specifications for the initial buildings. (Ord. 269 (part), 2002; Ord. 329 §1(part), 2006)