Zoneomics Logo
search icon

South Bound Brook City Zoning Code

§ 34-15.4

Time Limitation.

[Ord. 3/12/74, § 1004; Ord. 1/13/87, § 1004]
The Construction Official shall issue or deny a Zoning Permit within seven days of the application therefor where site plan approval by the Planning Board is not required and within seven days after affirmative action on the site plan by the Planning Board where site plan approval is required. The Construction Official shall issue or deny a Certificate of Occupancy within seven days of the application therefor where site plan approval by the Planning Board is not required, and within seven days after affirmative action on the site plan by the Planning Board where site plan approval is required.