§ 35-19.13

Conditions on Final Approval.

[1972 Code § 107-69; Ord. No. 1097]
The Planning Board may, as a condition of final approval:
a. 
Grant final approval only for designated geographic sections of the development.
b. 
Grant final approval for certain work but require resubmission for final approval for designated elements such as, but not limited to, landscaping, signs, street furniture, etc., and require approval of these elements as a prerequisite for a certificate of occupancy or zoning permit.
c. 
Condition the granting of a temporary certificate of occupancy or zoning permit on the applicant's or developer's or subsequent heirs' or assignees' meeting certain requirements within a designated period of time, not to exceed six months, from the date of issuance of the certificate of occupancy or zoning permit. This may include but is not limited to the installation of improvements, reevaluation of circulation patterns, etc.
d. 
Require the furnishing of a performance guaranty in favor of the Borough in an amount not to exceed 120% of the cost of installation for improvements it may deem necessary or appropriate, including streets, grading, pavement, gutters, curbs, sidewalks, streetlighting, shade trees, surveyor's monuments, as shown on the final map and required by the Map Filing Law, P.L. 1960, c. 141 (N.J.S.A. 46:23-9.9 et seq.), water mains, culverts, storm sewers, sanitary sewers or other means of sewage disposal, drainage structures, erosion control and sedimentation control devices, public improvements of open space and, in the case of site plans only, other on-site improvements and landscaping.
e. 
Require provision for a maintenance guaranty to be posted with the Governing Body for a period not to exceed two years after final acceptance of the improvement, in an amount not to exceed 15% of the cost of the improvement. In the event that other governmental agencies or public utilities automatically will own the utilities to be installed or the improvements are covered by a performance or maintenance guaranty to another governmental agency, no performance or maintenance guaranty, as the case may be, shall be required by the municipality for such utilities or improvements.
Site Plan Details