Development agreements.
In accordance with allowances made by state law, a property owner or developer may request, or the city may require, that an application for rezone or zoning map amendment be processed in conjunction with the execution of a development agreement. Through such agreements, a property owner or developer may agree to make written conditional commitments concerning the use or development of a subject parcel in exchange for the change of zoning requested. The purpose of such agreements shall be to allow development that provides benefits for both the property owner or developer and the city by providing a balance between the owner's or developer's desire for certainty in the development process and the city's desire for control of the impacts of the project.
Conditional commitments made under such agreements are in addition to the regulations provided for in the zoning district by ordinance, and are established to ensure compatibility of the resulting land use with the surrounding area. Unless multiple land use zones are used/applied within a project in accordance with that which is allowed by the table at section 10-3-2 of this title, the use of a PUD or MPC application process shall be the only means whereby the City of Nampa will/shall entertain allowing uses in a zone not normally allowed therein; development agreement conditions not excepting. The following rules shall govern development agreements:
A.
Creation and form. At a minimum, development agreements shall include the following: 1) a legal description of the subject property, 2) a description of the uses permitted on the land, 3) provisions for any reservation or dedication of land, 4) the duration of the agreement, 5) the commitments or other terms of the agreement. Furthermore, agreements shall include, if provided by an applicant and/or requested by the Planning and Zoning Commission and/or City Council: 1) a conceptual site plan showing proposed arrangement of any structure(s), business or industrial or multi-family park/complex freestanding signage, landscaping and parking area design(s); and/or 2) a set of building(s) elevations showing exterior building treatments and design(s).
B.
Commitments and safeguards. The written commitments or conditions exacted shall not be vague and shall have a reasonable relation to the zoning change approved. In addition, the following safeguards shall be applied:
1.
A development agreement shall only be allowed in connection with annexations or rezones applied for within bona fide transitional areas, i.e., where two or more competing and incompatible uses have valid claims.
2.
If a substantial amount of land surrounding a property zoned in connection with a development agreement is rezoned to the same zoning as originally requested for the subject property, said development agreement and the commitments contained therein may be lifted by the city upon request of the owner or developer after complying with the notice and hearing provisions of section 10-2-3 of this chapter.
3.
A development agreement shall not prevent the city in subsequent actions applicable to the property, from applying new rules, regulations or policies that do not conflict with commitments applicable to the property as set forth within any duly executed agreement.
4.
If a conditional commitment involves ongoing performance and the owner or developer fails to comply with the commitment after completion of construction, said failure may be dealt with by the city according to the violations and penalties provisions of section 10-2-6 of this chapter.
5.
When a commitment is required to be satisfied prior to completion of construction, and it is not so satisfied, construction shall be halted until compliance is established.
C.
Recording. Development agreements shall be attached as an exhibit to the ordinance establishing the zoning map amendment. Agreements shall take effect and shall be recorded in the Canyon County Recorder's office upon the adoption of the ordinance establishing the zoning map amendment by the city council. Should a development agreement be terminated by the city, and the zoning designation upon which the use is based be reversed, a document recording such termination and zoning reversal shall also be recorded by the city in the office of the county recorder unless otherwise modified or terminated by the city council. An agreement shall be binding on the owner of the parcel, each subsequent owner, and each other person acquiring an interest in the parcel.
D.
Modification, enforcement, termination and extension. Development agreements are generated at the time of annexation, pre-annexation or zoning map amendment requests. A modification of a development agreement can be requested at any time. Modification of and to an executed agreement shall be required by the planning director or his/her designee under the following circumstances:
1.
A substantial change to the conceptual layout, terms, provisions or conditions of the most recently recorded development agreement. These substantial changes could include but are not limited to:
• Exceeding the number of buildable lots;
• Decreasing the amount of approved open space;
• Revision of the approved open space concept;
• Revision of the approved set of building elevations;
• Items determined to be a substantial change according to the planning and zoning director or his/her designees.
In the event of default of this agreement, the city may provide written notice of said default. The owner/developer shall have 30 days after delivery of such notice to cure the default to the satisfaction of the city. In case the default cannot be cured within the 30 day period, the owner/developer may apply to the planning and zoning director, for a single six month extension. The decision to grant the extension is in the discretion of the planning and zoning director. No default by a subsequent owner of a portion of the property shall constitute a default by the original owner/developer. A subsequent owner may request extensions or modifications for their portion of the originally described property.
Upon default of a development agreement, a hearing for termination or modification may be convened by the city after complying with the notice and hearing provisions of subsection 10-2-2.C of this chapter and any relevant termination terms of the pertinent agreement. During the hearing, the council may vote to take no action, cause modification of the agreement if the applicant is willing, or terminate the agreement.
In accordance with state law, the establishment of a development agreement and the written commitments contained therein shall provide written consent for the city council to change the zoning of the subject property to its prior designation upon failure of an applicant to comply with the conditions imposed by their agreement.
E.
Application; filing fee. Prior to consideration of any petition or request for development agreement modification, an application for the request must be filed with the office of the planning director. The application shall be accompanied by a filing fee in an amount established by council resolution, and which is nonrefundable. The application shall be furnished by the city.
1.
Neighborhood meeting. A neighborhood meeting shall be conducted as outlined in subsection 10-2-2.B, planning application neighborhood meeting, of this title.
2.
Commission level public hearing required. Following proper advertisement of the request(s), per subsection 10-2-2.C, the commission shall conduct at least one public hearing during which the public shall have an opportunity to present their opinions on the matter(s) and the commission shall consider the proposed request(s). The commission shall make one or more recommendations on the request(s) to the city council. The commission shall either: recommend approval of the request(s), approval with modifications to the request(s), or denial of the request(s). Alternatively, they may vote to table or postpone taking action on the request(s).
3.
Public hearing required by council, notice. Development agreement modification requests may be adopted via ordinance only after a public hearing has been held. Notification of the city council public hearing shall follow the procedures outlined in subsection 10-2-2.C.
(Ord. No. 4617, § 1(Exh. A), 10-4-2021; Ord. No. 4843, §§ 9—11, 2-3-2025; Ord. No. 4873, § 5, 6-16-2025)