10-26-8

Procedure for PUD and MPC plan approvals.

A.

Planned unit development approval process.

1.

PUD permit. A PUD requires a PUD permit. A PUD permit is tied to the project and is valid for 18 months from the date that the PUD is approved by the planning and zoning commission. If a preliminary plat under that PUD is not submitted within the 18-month timeframe, the PUD expires. If a final plat under the preliminary plat is not submitted within 18 months, the preliminary plat and PUD expire.

2.

Preapplication meeting. The developer shall meet with the planning director or his/her designated staff prior to submission of an application. The purpose of this meeting is to discuss informally the purpose and effect of this chapter and the criteria and standards contained herein, and to familiarize the developer with the comprehensive plan, "zoning ordinance," "subdivision ordinance" and such other items as deemed appropriate.

3.

Application for a PUD permit.

a.

An application for a PUD permit shall be filed with the planning director or his/her designee by a property owner or person having existing interest in the property.

b.

The application shall be on a form as prescribed by the planning director and shall be accompanied by a nonrefundable fee as established by resolution of the council.

c.

The application for a PUD permit shall be accompanied by a written statement by the developer setting forth the reasons why, in his opinion, the PUD would be in the public interest.

4.

PUD development plan details. An applicant shall incorporate all PUD design elements into one preliminary development plan for presentation to the commission. The preliminary development plan shall be presented in the same form and contain the same information as outlined for preliminary subdivision plats under chapter 27 of this title. In addition, the development plan shall contain the following information:

a.

Location and type of land uses.

b.

Parks and community or open spaces.

c.

Notation(s) regarding proposed ownership of streets, public or private.

d.

A landscape plan, designed by a registered landscape architect or professional landscape designer, identifying materials and elements used for private and common open spaces, intervening spaces between rights-of-way and building lines, and between buildings, drives and parking areas.

e.

A description of the design principles for buildings and streetscapes; tabulation of the number of acres in the residential population by type of housing; estimated nonresidential population; standards for height, open space, building density, parking areas, population density and public improvements proposed for each unit of the development whenever the applicant proposed an exception from standard zoning districts or other ordinances governing development.

f.

Deed restrictions, protective covenants and other legal statements or devices to be used to control the use, development and maintenance of the land, and the improvements thereon, including those areas which are to be commonly owned and maintained.

g.

General outline of intended organizational structure related to property owners' association, deed restrictions and provisions of services.

h.

A copy of the legal title to the property or proof of a legally binding sales agreement ensuring the entire project area is under single ownership or control.

i.

Existing features of the development site including major wooded areas and structures.

j.

The pattern of public and private roads, driveways, parking facilities, pedestrian ways and intended design standards.

k.

The size arrangement and location of lots or of proposed building groups.

l.

The type, size and location of structures.

m.

The type, size and location of recreational and open space areas and areas reserved or dedicated for public uses such as schools, parks, etc.

n.

Site plan, showing building(s), various functional use areas, circulation and their relationship.

o.

Preliminary building elevation renderings/pictures/etc.

4.

Neighborhood meeting. A neighborhood meeting shall be conducted as outlined in section 10-2-2.B, Planning application neighborhood meeting, of this title.

5.

Public hearing procedures. When a public hearing is required by this chapter the same procedures for public hearing and legal notification, as required by chapter 25 of this title for conditional use permits, shall be followed.

6.

Design review required. Multi-family residential and commercial development shall be subject to design review.

7.

Commission action. Following application for PUD development plan approval, the commission shall review the development plan in accordance with the approval criteria set forth in this chapter and apply any necessary conditions of approval.

PUD approvals are valid for the life of the preliminary plat associated with it and will become permanent upon recordation of the first final plat for the development.

8.

Plat in lieu of a development plan and PUD permit. A preliminary plat may be submitted in lieu of a development plan with the PUD permit submittal materials. See section 10-27-2 of this title for preliminary plat form, content and process.

9.

Amendments. Any subsequent amendment to the approved development plan; changing location; positioning; and height of buildings and structures may be authorized by the commission as a business item without additional public hearings, if required, by engineering or other circumstances not foreseen at the time the development plan was approved. In no case shall the commission authorize changes which may, by reasonable judgment, expectedly cause any of the following:

a.

A substantial change in the use or character of the development.

b.

A decrease in common open space below that required in the project (e.g., via increase in overall coverage of structures).

c.

An increase in the intensity of any afore identified use(s) (e.g., via operating hours, trip traffic, building area increase, signage display, etc.) beyond that presented to the commission.

d.

An increase in the problems of traffic circulation and public utilities.

All other changes in use, rearrangement of lots, blocks, travel distances and building tracts, or in the provision of common open spaces and changes other than those listed above which constitute substantial alteration of the original plan, shall require a new public hearing before the commission.

B.

Master planned community approval process.

1.

Required approvals. An MPC requires an approved conceptual plan, approved annexation/rezone, and an approved development agreement.

2.

Preapplication meeting. The developer shall meet with the planning director or his/her designated staff prior to submission of the application. The purpose of this meeting is to discuss informally the purpose and effect of this chapter and the criteria and standards contained herein, and to familiarize the developer with the comprehensive plan, "zoning ordinance," "subdivision ordinance" and such other items as deemed appropriate.

3.

Application for an MPC.

a.

An application for an annexation/rezone and MPC shall be filed with the planning director or his/her designee by a property owner or person(s) having existing interest in the property.

b.

The application shall be on a form as prescribed by the planning director and shall be accompanied by a nonrefundable fee as established by resolution of the council.

c.

The application shall be accompanied by a statement by the owner/developer setting forth the reasons why, in his or her opinion, the MPC would be in the public interest.

4.

Conceptual plan. A conceptual plan approval is required prior to any preliminary plat approval. A preliminary plat may not be approved in lieu of a conceptual plan.

a.

Conceptual plan content. A master planned community conceptual plan for the entire MPC shall include the following information:

i.

"Bubble" diagram of the zoning, location, acreage and type of land uses.

ii.

Proposed densities and housing types for residential land uses for each area of the development.

iii.

The type, size and location of qualified and common open space areas with proposed recreational amenities and areas reserved or dedicated for public uses such as schools, parks, etc.

iv.

Notation(s) regarding proposed ownership of streets, public or private.

v.

The pattern of public and private roads, driveways, parking facilities, pedestrian ways and intended design standards.

vi.

General landscaping concepts with graphics showing landscape, street and central gathering area theme(s).

vii.

Existing features of the development site including major wooded areas, significant slopes, geological features and structures.

viii.

A statement or graphic drawing showing how special features of the site are to be highlighted or utilized.

ix.

Conceptual building elevation renderings/pictures/etc.

x.

A description of the smart growth principles that the MPC introduces into the plat design and how the plan integrates into the surrounding area and greater Nampa community.

xi.

A summary of the nature of the variations from zoning standards.

5.

MPC Development agreement. See section 10-2-5.B of this title.

6.

Neighborhood meeting. Applicant shall hold one neighborhood meeting with all property owners who reside within a 300 feet buffer area surrounding the project. The addresses of the invitees will be provided by the planning and zoning department (see section 10-2-3.B.1).

a.

Neighborhood meeting logistics.

i.

The applicant shall organize and conduct a neighborhood meeting regarding the project. The meeting shall be held after work hours, during the weekend or during a time when the greatest number of residents and interested parties can attend. The meeting shall be held at a location on site or within one mile of the project boundary.

ii.

The applicant shall advertise the meeting at least 10 calendar days in advance.

iii.

The meeting shall consist of a presentation about the conceptual plan, proposed land uses, residential density levels and features of the proposed development.

iv.

The applicant shall indicate to the residents the timing and logistics (phasing) of the project.

v.

The applicant shall address any concerns that the attendees may have.

7.

Public hearing procedures.

a.

An applicant shall submit a conceptual plan for review and recommendation by the commission, and approval by the council. If approved, the conceptual plan shall be included in a development agreement.

b.

The same procedures for public hearing for an annexation or rezone and development agreement in chapter 2 of this title shall be followed. An applicant may submit a preliminary plat or preliminary plats to the commission for approval as outlined in chapter 27 of this title concurrently with the annexation/rezone, and development agreement after the conceptual plan is approved.

8.

Commission/council action—Annexation/zoning and conceptual plan. Following application for an annexation/rezone and MPC, the commission shall review and make a recommendation to the council to approve or deny the annexation/zoning and MPC Conceptual Plan with any supplemental conditions in accordance with the approval criteria set forth in this chapter and the provisions outlined in chapter 2 of this title.

9.

Cause to enter into a development agreement. Approval of the city council of the annexation/rezone and MPC conceptual plan with any supplemental conditions attached thereto shall cause the city to enter into a development agreement for an MPC with the property owner/developer in accordance with the provisions outlined in chapter 2 of this title.

10.

Commission/council action—Preliminary plat approval.

a.

Following conceptual plan approval and completion of a development agreement, preliminary plats may be submitted for approval for specific development areas within the MPC (such as residential, commercial or industrial), or a preliminary plat may be submitted for the entire MPC development.

b.

Any preliminary plat submitted for a specific development area within an MPC, or for the entire MPC shall include a copy of the approved conceptual plan and a statement from the applicant indicating how the preliminary plan(s) meet(s) the conditions and features of the approved conceptual plan and associated development agreement. All preliminary plats are subject to the review and approval process outlined in sections 10-27-2 and 10-27-3 of this title.

c.

The commission shall review and approve or deny a/the preliminary plat(s) for the MPC in accordance with the approval criteria set forth and provisions outlined in chapter 27 of this title.

11.

Amendments. Any subsequent amendment to the final development agreement shall be subject to the provisions in section 10-2-5.D, Modification, enforcement, termination and extention, of this title.

C.

Industrial park approval process.

1.

Required approvals. An industrial park planned unit development or master planned community requires an approved conceptual plan from the Nampa Planning and Zoning Commission.

2.

Preapplication meeting. The developer shall meet with the planning director or his/her designated staff prior to submission of the application. The purpose of this meeting is to discuss informally the purpose and effect of establishing an industrial park and identify any challenges or need for exceptions.

3.

Application for an industrial park PUD or MPC.

a.

An application for an industrial park PUD or MPC shall be filed with the planning director or his/her designee by a property owner or person(s) having existing interest in the property.

b.

The application shall be on a form as prescribed by the planning director and shall be accompanied by a nonrefundable fee as established by resolution of the council.

4.

Conceptual plan content. The concept plan shall include the following information:

a.

The type, size and location of all building envelopes showing the orientation of the structures proposed. Identify the following:

i.

Primary facades to be reviewed per the definition in the design review guideline document and chapter 34.

ii.

Facades that may not need to be reviewed per the definition in the design review guideline document and chapter 34.

iii.

Locations of overhead doors.

b.

The pattern of public and private roads, driveways, parking facilities, pedestrian ways and potential amenities.

c.

General landscaping concepts with graphics showing landscape design, especially if the landscaping serves to screen utilities, overhead doors and/or facades or mitigate any design requirements. Include a statement or graphic drawing showing how special features of the site are to be highlighted or utilized for aesthetic or screening purposes.

d.

Existing features of the development site including major wooded areas, significant slopes, geological features and structures that may serve to screen certain portions of the proposed structures, making those facades unnecessary for design review.

e.

Conceptual building elevation renderings/pictures/etc.

f.

A summary of any exceptions requested from the standards in chapter 34.

4.

Neighborhood meeting. A neighborhood meeting is not required for any property already within the city limits and zoned IL (light industrial) or IH (heavy industrial) that is requesting approval as an industrial park for design review purposes. If the property requires annexation and zoning, a neighborhood meeting is required for the annexation application submittal.

5.

Public hearing procedures.

a.

An applicant shall submit a conceptual plan for review and approval by the commission. The approved concept plan will be used to assist in design review of any structure located within the boundary of the project.

b.

The same procedures for public hearing for conditional use permit in chapter 2 of this title shall be followed. An applicant may submit a preliminary plat to the commission for approval as outlined in chapter 27 of this title concurrently with the PUD/MPC application if they choose to subdivide.

6.

Amendments. Any subsequent amendment to the approved concept plan shall follow the same procedure again, as outlined in the previous section.

(Ord. No. 4617, § 1(Exh. A), 10-4-2021; Ord. No. 4702, § 1(Exh. A), 12-5-2022; Ord. No. 4777, § 1(Exh. A), 12-18-2023)