Storm Drain Pipe. All storm drain pipes shall be either slip joint type reinforced concrete or, subject to the restrictions herein, fully coated, invert paved, corrugated metal steel culvert pipe meeting the requirements of the standard specifications and of a wall thickness sufficient to meet the proposed conditions of service; but in any event, no wall thickness less than Class 3, Wall B, for concrete pipe or No. 14 gauge for corrugated metal steel pipe shall be allowed. Generally, concrete pipe will be used except in areas of steep grades or other restrictive physical conditions where corrugated metal or other types of pipe may be permitted. No concrete pipe may be laid on grades exceeding 10%. Concrete pipe below 30 inches (or equivalent) in size will be jointed using a mortared joint in accordance with the specifications. Concrete storm drain pipes, 30 inches or larger in diameter, will be jointed using a preformed bituminous mastic pressure-type joint sealer or rubber-ring-type or other equivalent approved joint. All corrugated metal pipe shall be fully bituminous-coated with paved invert and of a gauge meeting the requirements of the standard specifications sufficient for the proposed service. Where conditions permit, corrugated aluminum storm drains may be substituted for corrugated metal steel storm drains where the same is otherwise permitted on the basis of an equivalent three-edge bearing or crushed strength. Substitution on an equivalent gauge basis will not be allowed. All storm drains shall be tangent between inlets, manholes or other structures, except that the use of fittings or factory curved or mitered pipe may be allowed by the borough engineer when necessary to accommodate existing geometry or utilities. Prior to laying any storm drains, the bottom of all trenches shall be inspected by the borough engineer. Should the engineer determine that the trench is unsuitable for the placement of the pipe, the developer shall take all necessary action to remove or eliminate any unsuitable conditions. These may include, but are not limited to, excavation and backfilling with suitable material, placement of bedding material, construction of pipe cradles or such other action necessary to remove all unsuitable conditions. Proposed storm drainage installations which do not conform to the above must be fully detailed and approved as part of the final plat.