The final plat shall be drawn in ink on mylar or cloth at scale of not less than one inch equals 100 feet and in compliance with all provisions of the Map Filing Law (N.J.S.A. 46:23-9.9 et seq.). The following shall be shown on the final plat in order to be deemed complete by the Administrative Officer:
A title box containing the title of the map, the name of the development if applicable, the tax map sheet, block and lot numbers, and the names and addresses of the owner and of the subdivider, if different from the owner.
Certification by a surveyor authorized to practice in the State of New Jersey as to the accuracy of the details of the plat, and certification of engineering details by an engineer licensed in New Jersey.
Tract boundary lines, indicating the bearings of all lot lines and dimensions thereof, as well as the acreage of each lot and minimum building setback lines.
Right-of-way lines of all existing and proposed streets, easements and other rights-of-way, all with accurate dimensions and bearings and minimum widths as required by Borough standards.
Final construction plans providing all information required for preliminary plat. However, the plans shall be based on final elevations and final lot dimensions. The requirement for final construction plans may be waived by the Board if it can be determined that the preliminary plat was prepared to an accuracy and detail acceptable to the Borough Engineer.
Copies of all approval for sanitary sewer extension permits, stream encroachment permits, soil erosion and sediment control permits, Middlesex County Planning Board approval, and all other applicable approvals required for construction of the project from all other agencies with jurisdiction.
Certification that the applicant is the agent of or owner of the land, or that owner has given consent under an option agreement, or that the applicant is a contract purchaser or leasee. If the applicant is not the owner of record of the land, then all contractual agreements concerning its use shall be submitted.
A performance guarantee in favor of the Borough, and inspection fees if improvements have not already been constructed, approved as to size by the Borough Engineer and approved as to form by the Board Attorney.
Such other information as may be required by the Board in order to make an informed decision.
Milltown City Zoning Code
§ 34-16.4
Final Plat.
[Ord. No. 919 Art. XII, D]
The final plat shall be drawn in ink on mylar or cloth at scale of not less than one inch equals 100 feet and in compliance with all provisions of the Map Filing Law (N.J.S.A. 46:23-9.9 et seq.). The following shall be shown on the final plat in order to be deemed complete by the Administrative Officer:
A title box containing the title of the map, the name of the development if applicable, the tax map sheet, block and lot numbers, and the names and addresses of the owner and of the subdivider, if different from the owner.
Certification by a surveyor authorized to practice in the State of New Jersey as to the accuracy of the details of the plat, and certification of engineering details by an engineer licensed in New Jersey.
Tract boundary lines, indicating the bearings of all lot lines and dimensions thereof, as well as the acreage of each lot and minimum building setback lines.
Right-of-way lines of all existing and proposed streets, easements and other rights-of-way, all with accurate dimensions and bearings and minimum widths as required by Borough standards.
Final construction plans providing all information required for preliminary plat. However, the plans shall be based on final elevations and final lot dimensions. The requirement for final construction plans may be waived by the Board if it can be determined that the preliminary plat was prepared to an accuracy and detail acceptable to the Borough Engineer.
Copies of all approval for sanitary sewer extension permits, stream encroachment permits, soil erosion and sediment control permits, Middlesex County Planning Board approval, and all other applicable approvals required for construction of the project from all other agencies with jurisdiction.
Certification that the applicant is the agent of or owner of the land, or that owner has given consent under an option agreement, or that the applicant is a contract purchaser or leasee. If the applicant is not the owner of record of the land, then all contractual agreements concerning its use shall be submitted.
A performance guarantee in favor of the Borough, and inspection fees if improvements have not already been constructed, approved as to size by the Borough Engineer and approved as to form by the Board Attorney.