§ LU-146.5

Maintenance and Repair of Stormwater Management Systems.

[Added 10-25-2023 by Ord. No. 528-23; amended 9-4-2024 by Ord. No. 548-24]
a. 
All projects meeting the definition of Major Development, as defined in § LU-146.2, shall be required to include a maintenance and reporting plan as described herein.
b. 
The property owner, or design engineer, shall prepare a maintenance plan meeting the following requirements:
1. 
The maintenance plan shall contain specific preventative maintenance tasks and schedules; cost estimates, including estimated cost of sediment, debris, or trash removal; and the name, address, and telephone number of the person or persons responsible for preventive and corrective maintenance (including replacement). The plan shall contain information on BMP location, design, ownership, maintenance tasks and frequencies, and other details as specified in Chapter 8 of the NJ BMP Manual, as well as the tasks specific to the type of BMP, as described in the applicable chapter containing design specifics.
2. 
If the maintenance plan identifies a person other than the property owner (for example, a developer, a public agency or homeowners' association) as having the responsibility for maintenance, the plan shall include documentation of such person's or entity's agreement to assume this responsibility, or of the owner's obligation to dedicate a stormwater management facility to such person under an applicable ordinance or regulation..
3. 
Responsibility for maintenance shall not be assigned or transferred to the owner or tenant of an individual property in a residential development or project, unless such owner or tenant owns or leases the entire residential development or project. The individual property owner may be assigned incidental tasks, such as weeding a green infrastructure BMP, provided the individual agrees to assume these tasks; however, the individual cannot be legally responsible for all of the maintenance required.
4. 
If the party responsible for maintenance identified under subsection LU-146.5b2 above is not a public agency, the maintenance plan and any future revisions based on subsection LU-146.5b6 below shall be recorded upon the deed of record for each property on which the maintenance described in the maintenance plan must be undertaken.
5. 
Preventive and corrective maintenance shall be performed to maintain the functional parameters (storage volume, infiltration rates, inflow/outflow capacity, etc.) of the stormwater management measure, including, but not limited to, repairs or replacement to the structure; removal of sediment, debris, or trash; restoration of eroded areas; snow and ice removal; fence repair or replacement; restoration of vegetation; and repair or replacement of non-vegetated linings.
6. 
The party responsible for maintenance identified under subsection LU-146.5b2 above shall perform all of the following requirements:
(a) 
Maintain a detailed log of all preventative and corrective maintenance for the structural stormwater management measures incorporated into the design of the development, including a record of all inspections and copies of all maintenance-related work orders;
(b) 
Evaluate the effectiveness of the maintenance plan at least once per year and adjust the plan and the deed as needed;
(c) 
Retain and make available, upon request by any public entity with administrative, health, environmental, or safety authority over the site, the maintenance plan and the documentation required by subsection LU-146.5b5 and b6 above; and
(d) 
Obtain an annual stormwater maintenance permit from the Township in accordance with subsection LU-146.6.
7. 
The requirements of subsection LU-146.5b2 and b3 do not apply to stormwater management facilities that are dedicated to and accepted by the Township or another governmental agency, subject to all applicable municipal stormwater general permit conditions, as issued by the Department of Environmental Protection.
8. 
In the event that the stormwater management facility becomes a danger to public safety or public health, or if it is in need of maintenance or repair, the Township shall notify the responsible person in writing. Upon receipt of that notice, the responsible person shall have 14 days to effect maintenance and repair of the facility in a manner that is approved by the municipal engineer or his designee. The Township, in its discretion, may extend the time allowed for effecting maintenance and repair for good cause. If the responsible person fails or refuses to perform such maintenance and repair, the Township may immediately proceed to do so and shall bill the cost thereof to the responsible person. Nonpayment of such a bill may result in a lien on the property.
c. 
Nothing in this subsection shall preclude the Township in which the major development is located from requiring the posting of a performance or maintenance guarantee in accordance with N.J.S.A. 40:55D-53.